Home | | Visit OCC Site |

Project Documentation

Project Documentation

It is a condition of approval for the project that a number of documents are publicly available.

You can find these documents below as well as and links to other official documents on other websites:

PDF IconPre-Construction Compliance Report V5 (26 KB)

 

The Construction Environmental Management Plans were developed in line with the Department of Planning & Infrastructure as a set of guidelines to oversee the construction and monitoring of the project.

 

The following appendixes form parts of the CEMP for the construction of the pipeline and pump stations:

CEMP - Construction Environmental Management Plan - Rev 8 - Part 1

CEMP - Construction Environmental Management Plan - Rev 8 - Part 2

CEMP - Construction Environmental Management Plan - Rev 8 - Part 3

CEMP - Construction Environmental Management Plan - Rev 8 - Part 4

CEMP - Appendix S - PC&RMP's

CEMP - Appendix T - Part 1

CEMP - Appendix T - Part 2

CEMP - Appendix U - Alignment Reinstatement and Rehabilitation Rev 2

CEMP - Appendix U - Concrete Works

CEMP - Appendix U - Intermittent and Ephemeral Waterway Crossings - Rev 4

CEMP - Appendix U - Location of Services - Rev 2

CEMP - Appendix U - Macquarie River Site Access Track

CEMP - Appendix U - Macquarie River Site

CEMP - Appendix U - Overhead Powerlines

CEMP - Appendix U - Perennial Waterway Crossings - Rev 4

CEMP - Appendix U - Pipelaying - Rev 2

CEMP - Appendix U - Preliminary Works - Rev 3

CEMP - Appendix U - Weed & Bio Security Management - Rev 2

 


The following appendixes form parts of the CEMP for the construction of the new electrical infrastructure:

CEMP - New Electrical Infrastructure

Appendix B - Workplace Inspection Report (WIR)

Appendix C - Complaints Register

Appendix D - SWMS Template

Appendix E - Essential Energy Drawings

Appendix F - Traffic Control Plan

Appendix G - Poles and UG MOPP SWMP

Appendix H - Poles and UG MOPP NVMP

Appendix I - Poles and UG MOPP WMP

Appendix J Weed MPAppendix K FFMP

Appendix K FFMP

Appendix L - Poles and UG MOPP HMP

Appendix M - Waste Materials Record

Appendix N - External Correspondence

Appendix O - PCRMPs

 

The following appendixes form parts of the CEMP for the refurbishment of existing electrical infrastructure:

Essential Energy Environmental Impact Assessment

Essential Energy Project Safety and Environment Plan

 

The following documentation is provided as part of the Conditions of Approval:

Community Communication Strategy

Aquatic Environment Monitoring Program

Biodiversity Offset Package - Macquarie River to Orange Pipeline

SEWPaC Conditions of Approval

SEWPaC Compliance Report

 

Summary of Customer Complaints

Customer Complaints - December 2013 No complaints received during January 2015
2014 January - Summary Customer Complaints No complaints received during February 2015

 2014 February - Summary Customer Complaints

No complaints received during March 2015
2014 March - Summary Customer Complaints No complaints received during April 2015
2014 April - Summary Customer Complaints No complaints received during May 2015

 2014 May - Summary Customer Complaints

No complaints received during June 2015
2014 June - Summary Customer Complaints

No complaints received during July 2015

2014 July - Summary Customer Complaints

No complaints received during August 2015

2014 August - Summary Customer Complaints

No complaints received during September 2015

2014 September - Summary Customer Complaints No complaints received during October 2015
No complaints received during October 2014 No complaints received during November 2015
No complaints received during November 2014 No complaints received during December 2015
2014 December - Summary Customer Complaints No complaints received during 2016, updated 1/3/16

 


Annual Reviews

Condition of Approval C5 requires Orange City Council to submit an annual review to the satifaction of the Director General. Documents listed below.

Annual Review 18 June 2014 - received and satisfactory - Macquarie River to Orange Pipeline Project

Annual Review Report - Macquarie River to Orange Pipeline Project

Annual Review Report - 31 December 2014 - Macquarie River to Orange Pipeline Project

Aquatic Enviornment Monitoring B1

Condition of Approval C12(a)(v) requires Orange City Council to make available a comprehensive summary of the monitoring result relating to condition B1 Aquatic Environment Monitoring

Aquatic Monitoring Progress Report Macquarie Pipeline Dec 2014

Other Documents

Other documents are available for download through the Deparment of Planning and Infrastructure's website: http://majorprojects.planning.nsw.gov.au/index.pl?action=view_job&job_id=4475